Rooftop Solar Calculator Gujarat: What It Pre-Fills
This version of the calculator loads Gujarat's central subsidy rate, any state top-up rules and a local generation estimate, so you only enter your monthly units and roof area.
| Item | Gujarat (verify at publish) |
|---|
| Central subsidy | Up to Rs 78,000 |
| State top-up | Covers cost above your 10% share (5% SC/ST), systems up to 2.18 kWp |
| State benchmark cost | Rs 50,000/kW for first 2 kW, Rs 45,000/kW after |
| Applies to | Systems commissioned on or after 22 October 2026 |
| Lock-in | No further rooftop capacity for 3 years |
| DISCOMs | UGVCL, MGVCL, DGVCL, PGVCL, Torrent Power (Ahmedabad, Surat) |
| Nodal agency | GEDA |
Gujarat Solar Subsidy 2.18 kW: How the Top-Up Is Calculated
The state top-up is not a flat rate. It is whatever is left after the central subsidy and your capped share are taken from the benchmark cost.
| System | Benchmark cost | Central subsidy | Your share (10%) | State top-up |
|---|
| 1 kW | Rs 50,000 | Rs 30,000 | Rs 5,000 | Rs 15,000 |
| 2 kW | Rs 1,00,000 | Rs 60,000 | Rs 10,000 | Rs 30,000 |
| 2.18 kW | Rs 1,08,100 | Rs 63,240 | Rs 10,810 | Rs 34,050 |
| 2 kW, SC/ST (5%) | Rs 1,00,000 | Rs 60,000 | Rs 5,000 | Rs 35,000 |
Calculation for 2.18 kW: benchmark = 2 x 50,000 + 0.18 x 45,000 = Rs 1,08,100. Central = 2 x 30,000 + 0.18 x 18,000 = Rs 63,240. These are our calculations from the notified benchmark; confirm the exact amounts with your DISCOM at publish.
The catch competitors skip: the Rs 50,000/kW benchmark is well below current market prices, especially after the June 2026 domestic-cell rule. How a vendor quote above the benchmark is handled (vendor absorbs it, or you pay it) is not clear from published reports. Ask your vendor for a written all-in price before you sign.
Surya Gujarat Subsidy: What Changed
| Scheme | Status | What pages still say |
|---|
| SURYA Gujarat (40% up to 3 kW, 20% for 3 to 10 kW) | Ended, no longer paid as a separate top-up | Still widely quoted |
| "Rs 10,000/kW, max Rs 20,000" | Not confirmed in the current notification | Quoted by some guides |
| 2.18 kWp top-up (from 22 Oct 2026) | Current | Few pages cover it yet |
Solar Panel Price in Gujarat With Subsidy
| Line | 2 kW (top-up applies) | 3 kW (no top-up) |
|---|
| Market cost (Rs 65,000/kW) | Rs 1,30,000 | Rs 1,95,000 |
| Central subsidy | minus Rs 60,000 | minus Rs 78,000 |
| State top-up | minus about Rs 30,000 | Rs 0 |
| Net cost | about Rs 40,000 (Rs 10,000 if priced at benchmark) | Rs 1,17,000 |
Honest Trade-Offs in Gujarat
- The top-up stops at 2.18 kWp. A family needing 3 kW loses it entirely, so size carefully.
- The 3-year lock-in means you cannot add capacity soon after.
- Gujarat has India's highest rooftop adoption and a dense vendor market, so quotes are competitive.
Who Solar Suits in Gujarat
| Fit | Profile |
|---|
| Strong fit | Homes using 150 to 250 units a month that fit within 2.18 kWp |
| Marginal fit | Homes needing 2.5 to 3 kW (lose the state top-up) |
| Not a fit | Homes that installed recently and want to add capacity within 3 years |
Compare With Nearby States
Compare Rajasthan and Maharashtra, or go back to the main rooftop solar calculator.
FAQs: Solar Subsidy in Gujarat
How much is the solar subsidy in Gujarat?
Up to Rs 78,000 central for 3 kW or more. For systems up to 2.18 kWp commissioned from 22 October 2026, the state adds a top-up so you pay only 10% of the benchmark cost, or 5% for SC/ST households.
What is the Gujarat solar subsidy for 2.18 kW?
At benchmark prices, about Rs 63,240 central plus about Rs 34,050 state, leaving a consumer share of about Rs 10,810. Confirm exact amounts with your DISCOM.
Is the Surya Gujarat subsidy still available?
No. The earlier SURYA Gujarat state subsidy is no longer paid as a separate top-up. The current state support is the 2.18 kWp scheme.
Does a 3 kW system get the Gujarat state top-up?
No. The state top-up applies only to systems up to 2.18 kWp. A 3 kW system gets the central Rs 78,000.
Is there a lock-in after taking the Gujarat top-up?
Yes. Beneficiaries cannot add further rooftop capacity for three years from installation.
Can I get the top-up if I already have a small system?
Reports say yes, if your total capacity stays within 2.18 kWp after the new installation.
Which DISCOM handles solar in Ahmedabad and Surat?
Torrent Power serves parts of Ahmedabad and Surat. UGVCL, MGVCL, DGVCL and PGVCL serve the rest of the state.
Where do I apply for solar subsidy in Gujarat?
On pmsuryaghar.gov.in. Your DISCOM processes feasibility, net metering and the state top-up.